What a Full Home Renovation Really Involves: Coordinating 15 to 20 Trades
A full home renovation brings far more people through the door than most homeowners expect. On a house we are renovating in Oakville, our project manager Fravash counted every trade that has worked on it so far. He stopped at 17.
Here is who those trades are, the order they usually work in, and why coordinating them is the part of a renovation that matters most.

Who Works on a Full Home Renovation?
Framers, drywallers, plumbers, electricians, HVAC technicians, carpenters, kitchen installers, tile setters, painters, designers and engineers, plus inspectors at key stages. Each one depends on the trade before them finishing properly.
The Typical Order of Work
Every home is different, but most full renovations follow a similar sequence:
Demolition and design. The space is opened up and the plan is confirmed with the homeowner, designer and engineer where needed.
Framing. New walls, openings and structural changes are built.
Rough-ins. Plumbing, electrical and HVAC run through the open walls and ceilings.
Inspections. Permitted work is reviewed before anything is closed up.
Insulation and drywall. The walls are closed, taped and finished.
Flooring, cabinetry and tile. The finishes that define how the home looks and feels.
Trim, paint and fixtures. The final layer that makes the space feel complete.

Where Renovations Lose Time
Most delays don't come from the work itself. They come from the gaps between trades: one crew finishing late, a material arriving after the installer, or an inspection that has to be rebooked.
A good schedule keeps those gaps small. Each trade knows when they are needed, what has to be finished before they arrive, and who to call if something changes.
Small Habits That Prevent Big Problems
Before drywall goes up, we spray-paint the joist locations on the floor. Installers can see exactly where to fasten, which reduces the risk of drilling into wiring, plumbing or insulation hidden behind the walls.
At the rough-in stage of a bathroom, we plan for things a homeowner may want down the road, such as a dedicated electrical connection for a smart toilet. Adding it now costs little. Adding it later means opening finished walls.

What This Means for You
You should not have to manage 17 trades yourself. With a general contractor and a dedicated project manager, you have one point of contact who keeps everyone on schedule, checks the work at each stage and keeps you informed.

Frequently Asked Questions
How long does a full home renovation take?
It depends on the size of the home, the scope and permit timelines. Most full renovations run several months, and we set out a schedule with you before work begins.
Do I need permits for a full home renovation?
Structural, plumbing and electrical changes generally require permits and inspections. We plan these into the schedule from the start.
Can I live in my home during a full renovation?
Sometimes, depending on the scope. For a full gut, most homeowners find it easier and safer to stay elsewhere during the heaviest stages.